Ndizvo
Limited (UK) has completed contracts on behalf of Siemens
Plc and ABB for Freedom Maintenance who provide maintenance
for EDF Energy.

Stabilising existing flooring.
Key roles of the contract:
- Correct implementation of the Method
Statement, Risk assesments and the relevant Health
and Safety regulations.
- Ensuring close monitoring of works in
progress and cleanliness of site at all times in
case of emergency proceedures.
- Maintaining a high working standard.
|
|
| Site drawings were updated to show the
specific installation of the cross bracing. |
WE would
welcome the opportunity to work with you and solve
some of the problems that you have regardless of location
or complexity. |
|
|
Mid Contract: |
|
. |
Mid Contract:
Loose tiles were covered to avoid trips
and falls and the site cleaned to ensure optimum access.
|
Completion of Contract:
|
|
At the completion of the contract the
"safe to remove tiles" were marked and notices
errected informing persons of safe access areas and
the necessary documents passed to key personel.
|
Panel Supports:
|
|
Panel bases/supports were also built..
|
Job Satisfaction:
|
|
" Thanks for the excellent job done in
my absence, EDF reported to me that the job was completed
to a good standard and on time."
|
|